October 2014 |
[an error occurred while processing this directive] |
|
Global Pharmaceutical Manufacturer saves $152,173 in annual energy costs in a single R&D building.
Articles |
Interviews |
Releases |
New Products |
Reviews |
[an error occurred while processing this directive] |
Editorial |
Events |
Sponsors |
Site Search |
Newsletters |
[an error occurred while processing this directive] |
Archives |
Past Issues |
Home |
Editors |
eDucation |
[an error occurred while processing this directive] |
Training |
Links |
Software |
Subscribe |
[an error occurred while processing this directive] |
Overview
This Global Pharmaceutical
Manufacturer (GPM)* is one of the largest pharmaceutical companies in
the world. *Due to confidentiality agreements, we are not able to
provide the
client name. We will refer to the firm as GPM throughout this case
study.
The Challenge
GPM had a global objective of reducing greenhouse gas emissions and energy consumption by 20% from 2012 levels, by 2020.
To this end, GPM was interested in implementing energy conservation
measures and technologies, which help achieve these goals while
improving the overall reliability of their operations.
Results achieved
* Energy savings financial summary
* Energy savings: $152,173 (annual)
* Simple payback: 0.19 years
* Net present value: $177,856
* Other operational benefits
* Improved sustainability and environmental stewardship.
Achieved 800+ tons in annual CO2 emissions reduction, which is the
equivalent of taking 170 cars off the road.
* Increased staff and contractor productivity. Quantification of
savings for each opportunity allowed for prioritization of workload.
Root cause analysis provided by Analytika allowed maintenance staff and
contract automation personnel to target their efforts and work more
efficiently. Productivity as measured by savings achieved per hour
improved by over 30%.
* Improved central plant load capacity by more than 10%.
Reduction in building side energy consumption allowed central plant
capacity to be utilized elsewhere.
Cimetric' Solution
Cimetrics was selected to provide its Analytika Pro solution for a
100,000 square foot, laboratory and office building, which is part of a
one million square foot manufacturing, R&D and office campus.
Cimetrics collaborated with GPM and their building automation system
providers, Johnson Controls and Schneider Electric, to connect to and
collect sensor and actuator data from almost 5,000 physical
points. Data was collected every 15 minutes, 24 hours a day, 365
days a year - averaging approximately 480,000 data samples per
day. The following systems were monitored: 3 Air Handling Units,
2 Hot Water Pumps, 2 Chilled Water Pumps, 10 Fan Coil Units, 29 Fume
Hoods, over 400 Terminal Units, and other miscellaneous equipment.
Over 1,000 Fault Detection and Diagnostic algorithms then analyzed the
data to identify opportunities to reduce energy, improve environmental
conditions and reduce maintenance, operations and regulatory
costs. Analytika also uncovered potential equipment problems and
identified opportunities for operational uptime improvements and
profitable retrofit projects.
Experienced Cimetrics engineers leveraged Analytika software to
identify opportunities, determine root cause, and calculate annual
savings impact for each identified opportunity. Actionable
recommendations were documented and provided to the client both online
through the Analytika web based portal and offline through periodic
reports. Cimetrics' role didn't end at recommendations. Cimetrics
engineers met with the client team on a regular basis to help answer
technical questions, coordinate implementation, and provide regular
feedback on progress.
Example issue:
Inlet guide vanes not operating correctly
Two large air handlers (AHUs) in the building with inlet guide vanes
(IGVs) were operating at higher flows than required. This issue
was not detected at the site as adequate temperature and humidity
conditions were maintained in the zones. However, Analytika determined
that zone conditions were not being achieved in the most efficient way
possible.
[an error occurred while processing this directive]Solution
Cimetrics recommended replacing the IGVs with VFDs to achieve savings
and provide better airflow control. Cimetrics provided technical
guidance and helped coordinate the activities of the GPM staff and the
controls vendor. Furthermore, the ongoing monitoring provided by
Analytika allowed GPM to qualify for utility incentives to help pay for
the upgrade and Cimetrics helped GPM secure the incentive. This
opportunity reduced energy costs as well as annual maintenance costs
going forward.
Energy savings for solution: $27,503 (annual)
Utility incentives secured: $6,300
For more information visit http://www.cimetrics.com
or Email: products@analytika.com
[an error occurred while processing this directive]
[Click Banner To Learn More]
[Home Page] [The Automator] [About] [Subscribe ] [Contact Us]