August 2014 |
[an error occurred while processing this directive] |
The Importance of Mechanical Details
The devil is in the details |
Steven
R. Calabrese |
Articles |
Interviews |
Releases |
New Products |
Reviews |
[an error occurred while processing this directive] |
Editorial |
Events |
Sponsors |
Site Search |
Newsletters |
[an error occurred while processing this directive] |
Archives |
Past Issues |
Home |
Editors |
eDucation |
[an error occurred while processing this directive] |
Training |
Links |
Software |
Subscribe |
[an error occurred while processing this directive] |
Whenever I’m bidding a plan/spec project, the first thing I do is print
out the mechanical plans. Which is easier said than done if there are
dozens and dozens of them! The point is, some of the plans are, shall
we say, less important than others. For instance, if demolition plans
are included in the mechanical set, and I’m excluding anything to do
with demo, then I may choose not to print out these particular sheets
in full-size format. Other plans, such as ventilation schedules, may
have little to no significance to what I need to know in order to
accurately quote the project from a controls perspective.
Mechanical details typically take up one or two sheets of the
mechanical plans of any given plan/spec job. My first instinct is
always to ignore these sheets. Get to the heart of the project by
studying the floor plans, piping/ventilation schematics, and equipment
schedules. However my better judgment always leads me back to these
drawings, as I’ve been burned in the past by disregarding them as
“mechanical” information with no relevance to controls.
So the purpose of this column is to explore these details, in a general
manner, and point out some items that relate to the temperature
controls scope of any given project. As we will see, there are little
things “hidden” in these details, that may not be included anywhere
else in the plans and specifications, and they need to be accounted
for. Moreover, there may even be inconsistencies between these details
and information included elsewhere in the contract documents. In any
case, these things need to be addressed, accounted for, quantified,
clarified, etc. In the end, the consulting engineer will hold you to
the information included in these details, so it’s best to be aware of
their importance, and to give them equal consideration in the contract
document review process.
Coil Details
You’ve seen them. An isometric depiction of a hot or chilled water
coil, with piping and all the amenities. The purpose of these details
is to show what simply cannot be shown on the floor plan representation
of the coil, which is typically internal to a piece of equipment or
some ductwork. The main thing for the controls contractor is the
configuration of the control valve, be it two-way, three-way mixing,
three-way diverting, modulating, two-position, etc. This is where you
find this critical piece of information, if nowhere else. If indicated
elsewhere on the plans, then this serves as verification. If
inconsistent with what is found elsewhere, then it’s a matter of
seeking out clarification on the issue.
Also frequently found on the coil detail are the locations of
temperature sensors. The detail that I’m currently looking at as I
write this column shows an immersion sensor on both the inlet and the
outlet of the coil. However when I check the points list in the
temperature controls specification for this project, I do not find a
requirement for coil temperature sensing points. Since this is a single
instance on this particular project, I’m accounting for it as it won’t
drastically affect my price and scope. Yet if there were dozens of
these coils, I may reconsider and ask for clarification before I
generate a bid. As you can see, these details are important as well as
they are sometimes confusing and contradictory to other information
found in the contract documents.
You may find other items such as flow meters, BTU meters, and drainpan
detectors shown on the coil details and not found anywhere else. It’s
acceptable for these types of devices to be only shown on the details.
In fact if that’s the only place they’re indicated, then there’s no
inconsistency. If they are indicated elsewhere, then again the coils
detail serves to confirm the need.
Pump Details
Staying on the waterside, we consider pump details, those depicting
either a base-mounted or inline pump, with the mechanical (piping)
trim. Sometimes these details will include flow switch and temperature
sensor locations. I’ve found that often these details will be generic
in nature, and may or may not be in alignment with what’s called for in
the specs. The last time I saw pump status proved by a flow switch was
in nineteen ninety whaaat? More recently, I’ve seen pump status called
for to be proven by a differential pressure switch across the pump, and
I still see details that indicate this. These days we’re inclined to
confirm status of any motor, be it a pump or a fan, by using a
current-sensing switch. Regardless of what some pump detail may show.
Exhaust Fan Details
Turning to the airside, the first that comes to my mind is the exhaust
fan detail. Whether roof-mounted, sidewall, or inline, there are things
to look for and be mindful of. With roof-mounted exhaust fans, the
detail may show a backdraft damper, whether motorized or gravity. The
detail that I’m looking at now does not specify, and so I may need to
go elsewhere for this information, like the equipment schedule. Which
begs the question, “Who’s responsible for providing the damper”. If
it’s a gravity damper then I’ll exclude it, as it is technically not a
control device. However if it’s to be a motorized damper, then either
I’m to provide it, or it’ll come from the factory, as part of the
exhaust fan assembly. Same goes for side-wall fans. Is there a damper?
Is it motorized? If so, who’s to provide?
Terminal Unit Details
For VAV and fan-powered boxes, the temperature control points are
generally accepted and often included in a points list for these
equipment. Still, it’s good practice to review the details, as I’ve
found anomalies that I’ve needed to be aware of. Discharge air
temperature sensors shown on units with heating coils, for example. No
need to provide a discharge air sensor if the VAV box is cooling-only,
I’m sure we’ll agree with. But if the unit has an electric or hot water
coil, the detail may show this, even if the points list omits it. The
other one that creeps up is the requirement for a pressure-independent
control valve. This will typically be written up in the spec, yet may
also be indicated in the terminal unit detail (or not!).
Miscellaneous Details
[an error occurred while processing this directive]
Other details often contain information pertinent to the controls
contractor. We’re familiar with the typical boiler and chiller system
details, those that are schematic in nature in order to show the design
concepts of the hot or chilled water systems that they depict. Included
in these details are sensor locations, be it both temperature and
pressure. Also shown are control valves that don’t associate with any
particular coils, such as system bypass valves and boiler/chiller
isolation valves. These control valves are often large in size, so
don’t miss these!
Packaged unit details, such as those for rooftop units and packaged
make-up air units, may provide some additional insight as to what’s
required. For instance, the equipment schedule for the rooftop units
may indicate in the notes that a duct-mounted smoke detector is
required for all units over 2,000 CFM. The detail may show where that
detector is to be located. With any air handler of substantial size,
there’s always the possibility of having to furnish and install airflow
measuring stations, especially if the project is striving to achieve
LEED certification. It is possible that the only place this is shown is
on the equipment detail.
The devil is in the details…literally! Ignoring these all-important
sheets of the mechanical plans, when procuring a contract for the
installation of the temperature control systems, can lead to being
awarded the project, only to find out that you’ve underbid because you
missed some big-ticket items shown only on the mechanical details!
Tip of the Month: Find the details sheets of any given plans and
specifications project, and highlight anything remotely associated with
controls. Make a list of these items and keep the list handy. Use the
list as a reference of what you should be looking for on the details
sheets of future projects. Update the list whenever you find something
new. In the long run, this list may just help you procure a project, or
at the very least keep you out of trouble!
[an error occurred while processing this directive]
[Click Banner To Learn More]
[Home Page] [The Automator] [About] [Subscribe ] [Contact Us]