May 2010 |
[an error occurred while processing this directive] |
The “preconstruction” phase of a project, (Part 1 of 3) |
|
On the heels of last month’s article on installation (part 2 of 3), we now turn our attention to the final phase, and often the longest phase, of any given project. From punch lists to final closeout documentation, this phase is frequently wrought with complexities that make it difficult, if not downright nearly impossible, to close the books on a project and collect final payment. Yet if approached thoughtfully and implemented properly, this all-to-often neglected phase of a project can be turned out in short order, and all involved can “part ways”, at least until the next one!
[an error occurred while processing this directive] |
[an error occurred while processing this directive] |
This month’s installment, the final of a three-part series on controls contracting operations, examines just a few of the items and issues required to be addressed at the closeout of any project.
Punch Lists
Kind of an off-putting term for a list of items required to be completed in
order to close out a project, huh? Maybe the term originated from the prospect
that once upon a time, items completed on these lists were “punched out” with a
hole puncher in order to keep track of what was completed and what still needed
to be done. Maybe not, but at least in a figurative sense, I suppose.
So punch lists contain tasks that, so to speak, “rise to the top” at the end of
a project. Items that are missed, neglected, or items that simply arise due to
the nature of the project. It is understood by all that these items need to be
completed in order for all contractors to be fully compensated. What’s not as
easily understood at times is whose responsibility is what, with regard to items
that more or less “tow the line” between two trades. That said, it is in
everyone’s best interests at this point in the project to put aside any
disparity and work together to get through the punch lists, so that the project
can be completed and everyone can go home!
With regard to controls installations, punch list items are typically minor, and
can include any or all of the following: cable tagging, panel wiring cleanup,
missing junction box covers, missing and/or broken thermostats and space
sensors, etc. Sometimes larger items find their way onto these punch lists, that
are more or less scope items that have been missed and are still owed by the
contractor. And sometimes those items are disputable, leading to an ongoing
debate on whether it’s owed or extra. You can see by this, just how these punch
lists can linger, long after the dust has cleared and the equipment has left the
jobsite.
Commissioning
[an error occurred while processing this directive]
Commissioning means different things to different people. In the controls
contracting arena, it basically means checking out all points and validating
Sequences of Operation. Back in another lifetime I worked for a company that had
a three-tiered commissioning process, probably not unlike many other companies’
commissioning processes. In this model, the first tier, or level, deals with
ensuring that all hardwired points are indeed present as per the contract
documents, and installed in compliance with the project specifications. The
second level deals with configuring, calibrating, and validating the
functionality of all points connected. And the third level deals with ensuring
that all equipment operation is in alignment with the Sequences of Operation.
“Level 3” commissioning encompasses checkouts on a project-wide,
system-by-system basis, and includes validation of normal operating sequences,
startups and shutdowns, interlocks (both hardware and software), and failure
modes as defined in the contract sequence specifications.
Of course these days with so many projects striving for LEED certification, the
commissioning process has taken on a whole new meaning, encompassing not only
controls but many other facets as well. For the controls contractor, LEED
certification often means the involvement of a commissioning agent, that will
require the controls contractor to perform commissioning tasks that could be
considered “above and beyond” what has been historically required. Not that
that’s a bad thing. On the contrary, however the controls contractor, and other
contractors as well, need to understand this and be prepared for it.
End User Training
To achieve owner buy-in of the control systems installation, owner training must
be performed. This typically takes the form of several on-site sessions with
members of the facility’s maintenance staff, and often an “opposite season”
session is required 4-6 months subsequent to the initial training that should be
performed at the close of the project. It is important for the owner’s chosen
trainees to understand the importance of this training, invest their time in it,
and focus on the training at hand (easier said than done!).
Front-end, or operator workstation training, deals with educating the customer
on how to navigate his building automation system graphics package. This
includes the basics such as logging on and off, security levels, and browser
functions, and then moves in to navigation issues such as getting past the home
page, to the floor plans, drilling down to the major equipment graphics (central
station air handlers and boiler/chiller plants), and even further down to the
zone level graphics (VAV boxes, fan coils, etc.). Finally, scheduling features
and functions need to be covered, as well as generating reports, setting up and
interpreting trend logs, and alarms notification and acknowledgment.
Tip of the Month: Just because a project is done and over with doesn’t mean that you can toss the files on it! Stating the obvious, but for a reason. The point being, you can’t hold on to everything forever. And while computer storage is ever-increasing, just how many old files do you really want to hold on to and manage? And what about hard files? Perhaps the best we can do these days is maintain a filing system of both hard and soft files, the hard files mainly consisting of printouts of the as-builts, and the soft files containing everything else pertinent to the project and in electronic form. Gone are the days of maintaining huge manila folders with tons of paperwork, and thank goodness for that! |
One thing that should not be overlooked during this
phase is overall training on the basics of the mechanical systems and equipment.
Whether done before or in conjunction with the basic “front-end” training, this
needs to get done. No sense in getting trained in how to use the navigation
graphics package if you don’t understand the basics of the mechanical systems
and equipment that are depicted within the package, right?
Closeout Documentation
So if you took the lead from last month’s column and kept up on your
documentation throughout the course of the project, then it should be no problem
to incorporate any and all changes made, into the drawing set and Sequences of
Operation. This of course is so that you can generate the final set of
documents, or the “as-builts”, that serve as the final record and get turned
over to the customer at the close of the project. This is important for many
reasons, and sometimes (oftentimes?) it is not performed to the caliber that it
deserves to be, for whatever reasons. Nevertheless, this documentation, if given
the proper attention and assembled with accuracy, will serve a great purpose for
the foreseeable future of the facility and its systems.
Last but not least is the Letter of Warranty. Most projects are required to be
warranted for a year after the date of final completion. That date needs to be
put forth by the general contractor, such that all contractors under the general
can warranty their systems and equipment from that point forward. The warranty
letter is more or less a formality of this procedure. The letter is written by
the contractor, is sent to the customer, and simply serves to document the
warranty period.
[an error occurred while processing this directive]
[Click Banner To Learn More]
[Home Page] [The Automator] [About] [Subscribe ] [Contact Us]