September 2018
AutomatedBuildings.com
|
[an error occurred while processing this directive]
(Click
Message to Learn More)
|
This is a
companion to last month’s “Art and Science of Point
Selection” column. The sequence of operation (“sequence”) is the
most important aspect of BAS design. BASs require extensive
sequence programming by the installer to transform it from a pile of
electronics into the brain of an HVAC operation. As with
point selection, sequence writing: 1) Requires an “art and science”
approach, and 2) Is an iterative process with the point
selection. So this column won’t provide much detail about these
aspects (revisit last month’s column, if necessary) but instead will
focus on the key aspects unique to sequences.
Important Considerations –
There are four objectives that a sequence needs to address:
- Equipment Protection – The sequence must include protection to
minimize damage to equipment, such as freezing coils, short-cycling
motors, duct damage due to over/under pressurization, etc. This
objective is not optional and cannot be traded off for more-easily
meeting the remaining objectives.
- Reliable Operation – Each building and building use will have a
different definition of “reliable” (i.e., ranging from a high tolerance
to periods of degraded interior conditions to the nearly 0% system
downtime for a top-tier data center). The sequence needs to
address the project’s definition of reliability, which is also not an
option.
- Comfort – Indoor temperatures, RH, and air quality need to be
maintained at reasonable levels. These attributes have a range of
acceptable values, which, along with owner’s willingness to tolerate an
even wider range, can be balanced with the next objective.
- Energy Efficiency – Increasing system efficiency can be a
balancing act with comfort. Unfortunately, it is not always clear
which sequence choices will improve efficiency and/or if they will be
so complicated that it can affect reliability or even equipment
protection.
The Process of Writing Sequences
- Start with a schematic diagram and initial point list of the
systems to be controlled.
- The initial point list should take into account (this was also
discussed in my last column):
- Which factory-provided equipment safeties or controls will be
used as-is vs. bypassed for control by the BAS. If used as-is the
only points included should be for monitoring safeties and controls as
well as providing supervisory control of the factory controls (e.g.,
on/off, setpoint reset, etc.); and
- Which factory-provided controls are to be interfaced via points
vs. digital communications (e.g., BACnet).
- As with the point list, develop the sequences “top-down” – list
all unique systems, then their components, and then the controlled
devices (e.g., VFD’s, damper/valve actuators, etc.).
- For each component/device (or a logical group of
components/devices) describe the normal mode of operation (e.g.,
unoccupied vs. occupied) and abnormal modes (e.g., failures,
alarms). The latter needs to address the equipment safety
requirements, while all modes need to meet the project reliability
objective while achieving the project’s comfort vs. energy efficiency
balance.
- Review the point list to ensure it can fully address the
sequence, then review the schematic diagram to ensure that the sequence
and points match the mechanical design.
- Continue iterating this sequence vs. objectives vs. point list
& schematic diagram comparison, and edit them further until they
are all in agreement and meet the project’s objectives.
[an error occurred while processing this directive]Example – The following is an
abbreviated example of what the above process might result in for a
simple single-boiler heating plant:
- Boiler
a. Occupied Mode
Start/Stop
i. Start when OAT is
under 65 deg. F.
b. Unoccupied Mode Start/Stop
i. Start when OAT is
under 45 deg. F.
- Pumps
a. Constant Volume
Primary Pump
i. Interlock to boiler
b. Variable Volume
Secondary Pump
i. Interlock to
boiler and modulate VFD to maintain loop diff. pressure
- Mixing Valve
a. When boiler is on
modulate to maintain the HWST to the reset schedule…
4. Failure Alarm –
Issue alarm when boiler failure is detected
Closing Thoughts – Sequence
development, as with point list selection writing, has become more
challenging over the years. This column has previously discussed
the hope that ASHRAE Guideline 36 (“High-Performance Sequence of
Operations…”) can help with this challenge. Keep your fingers
crossed!
footer
[an error occurred while processing this directive]
[Click Banner To Learn More]
[Home Page] [The
Automator] [About] [Subscribe
] [Contact
Us]