Tweet

September 2018
AutomatedBuildings.com

[an error occurred while processing this directive]
(Click Message to Learn More)


Back to BASics:

Sequences of Operation

Ira Goldschmidt

Ira Goldschmidt, P.E., LEEDŽAP
Engineering Consultant,
Goldschmidt Engineering Solutions
ira.goldschmidt@comcast.net

Contributing Editor


As published

Engineered Systems 
September Issue - BAS Column
 
Articles
Interviews
Releases
New Products
Reviews
[an error occurred while processing this directive]
Editorial
Events
Sponsors
Site Search
Newsletters
[an error occurred while processing this directive]
Archives
Past Issues
Home
Editors
eDucation
[an error occurred while processing this directive]
Training
Links
Software
Subscribe
[an error occurred while processing this directive]

This is a companion to last month’s “Art and Science of Point Selection” column.  The sequence of operation (“sequence”) is the most important aspect of BAS design.  BASs require extensive sequence programming by the installer to transform it from a pile of electronics into the brain of an HVAC operation.   As with point selection, sequence writing: 1) Requires an “art and science” approach, and 2) Is an iterative process with the point selection.  So this column won’t provide much detail about these aspects (revisit last month’s column, if necessary) but instead will focus on the key aspects unique to sequences. 

Important Considerations – There are four objectives that a sequence needs to address:

  1. Equipment Protection – The sequence must include protection to minimize damage to equipment, such as freezing coils, short-cycling motors, duct damage due to over/under pressurization, etc.  This objective is not optional and cannot be traded off for more-easily meeting the remaining objectives.
  2. Reliable Operation – Each building and building use will have a different definition of “reliable” (i.e., ranging from a high tolerance to periods of degraded interior conditions to the nearly 0% system downtime for a top-tier data center).  The sequence needs to address the project’s definition of reliability, which is also not an option.
  3. Comfort – Indoor temperatures, RH, and air quality need to be maintained at reasonable levels.  These attributes have a range of acceptable values, which, along with owner’s willingness to tolerate an even wider range, can be balanced with the next objective.
  4. Energy Efficiency – Increasing system efficiency can be a balancing act with comfort.  Unfortunately, it is not always clear which sequence choices will improve efficiency and/or if they will be so complicated that it can affect reliability or even equipment protection.

The Process of Writing Sequences

  1. Start with a schematic diagram and initial point list of the systems to be controlled.
  2. The initial point list should take into account (this was also discussed in my last column):
  1. As with the point list, develop the sequences “top-down” – list all unique systems, then their components, and then the controlled devices (e.g., VFD’s, damper/valve actuators, etc.).
  2. For each component/device (or a logical group of components/devices) describe the normal mode of operation (e.g., unoccupied vs. occupied) and abnormal modes (e.g., failures, alarms).  The latter needs to address the equipment safety requirements, while all modes need to meet the project reliability objective while achieving the project’s comfort vs. energy efficiency balance.
  3. Review the point list to ensure it can fully address the sequence, then review the schematic diagram to ensure that the sequence and points match the mechanical design.
  4. Continue iterating this sequence vs. objectives vs. point list & schematic diagram comparison, and edit them further until they are all in agreement and meet the project’s objectives.

[an error occurred while processing this directive]Example – The following is an abbreviated example of what the above process might result in for a simple single-boiler heating plant:

  1. Boiler
a.    Occupied Mode Start/Stop
i.    Start when OAT is under 65 deg. F.
b.    Unoccupied Mode Start/Stop
i.    Start when OAT is under 45 deg. F.

  1. Pumps
a.    Constant Volume Primary Pump
i.    Interlock to boiler
b.    Variable Volume Secondary Pump
i.    Interlock to boiler and modulate VFD to maintain loop diff. pressure
  1. Mixing Valve
a.    When boiler is on modulate to maintain the HWST to the reset schedule…

   4.    Failure Alarm – Issue alarm when boiler failure is detected

Closing Thoughts – Sequence development, as with point list selection writing, has become more challenging over the years.  This column has previously discussed the hope that ASHRAE Guideline 36 (“High-Performance Sequence of Operations…”) can help with this challenge.  Keep your fingers crossed!

footer


[an error occurred while processing this directive]
[Click Banner To Learn More]

[Home Page]  [The Automator]  [About]  [Subscribe ]  [Contact Us]

Events

Want Ads

Our Sponsors

Resources